Some notes on moving MetroClusters.
Scenario. A customer is moving from one datacenter to the other. They have 2 MetroClusters (one IP, one FC), so we'll need to do some switchovers and get the hardware moved to the new site, then re-commission in the new site.
Information to Acquire and Review Before Planning Call
- The official documentation (which is important to follow closely for NetApp Support requirements) is here:
- Power off and power on a single site in a MetroCluster FC configuration
- Power off and power on a single site in a MetroCluster IP configuration
- Review the NetApp | Active IQ health status of the MetroCluster systems (check if any remediations need to be done before the move)
- NetApp - Active IQ Config Advisor output
- Similar to above, review any remediations.
- NetApp ConfigBuilder > Report > NetAppDocs As-Built : outputs (nice to have)
- Valid Support status (needs to be under hardware support, and make sure support are informed that it is moving).
Questions at Planning Call Before Move
- Site address for old and new sites?
- Technical contacts?
- What is the plan for moving the ISLs?
- Will we need to move ISLs to new external ports at UP site?
- [FC] What is the distance of the new ISLs (might need to reconfigure the Fabric Switches)?
- Rack space and power in new site?
- Networking in new site (will we need to re-IP anything)?
- Date and time?
To be continued ...